🌙 Technical Issue at Shorabak Power Plant Resolved 📆 Date: July 3–4, 2025 According to the pre-planned maintenance schedule, repair work on Unit 1 of the Shorabak Power Plant was carried out at 11:00 PM on July 3. The technical steps taken are as follows: 🔧 A spring washer was installed to stop water leakage in the water bearing. 🔩 Twelve washers were installed in the water bearing. 🛠 The runner blade was inspected, adjusted, and greased with 30 liters of VG150 oil. ⚙ The lower bearing of the unit was also technically checked. ✅ Finally, at 6:20 PM on July 4, the unit was successfully restarted and reconnected to the city grid. These maintenance actions are an important step toward the stable operation of the plant and a reliable power supply to the network.